Scope of Works
Thorpe Park needed a floating platform to help install a scaffold onto one of the bridges crossing the lake, ahead of winter works. The pontoon is on hire from mid-November through to early March, so it had to be stable and safe to work from over a long period. It also needed edge protection around every exposed edge and had to carry the scaffold tower being built from it.
Access was the other challenge. Vehicles and trailers could reach the southern end of the car park, but the bridge sits some way across the lake, so the pontoon couldn’t be delivered and installed beside it. It had to be launched from the slipway and moved across the water to its working position at the bridge.
Solution
Floating Pontoon Hire supplied a 200 m² modular pontoon with edge protection fitted to all exposed edges, giving the contractor a large, level platform beneath the bridge. The pontoon was delivered to the southern end of the car park and launched from the slipway. A pontoon raft carried it across the lake to the entrance bridge, where it was positioned alongside the bridge for the scaffold build.
The modular system suits a long winter hire, because the whole working area is covered in one installation and the edge protection makes it safe to work from over open water. The works are ongoing, and the pontoon will be recovered by the same route once the scaffold is removed.